The architectural set is nearly complete, the stair is framed, and the railing elevation still carries a note that reads "height per code." Many custom railings go wrong at that note. Stair railing height is not one dimension. A stair can carry a handrail you hold and a guard that keeps you from falling off an open side, and the two follow different rules, are measured from different lines and may be the same piece of wood or two separate ones.
Sorting that out before fabrication saves rework, especially on custom rails where the cap, newels and balusters are made to order and cannot be trimmed on site without consequences. For reference, the model residential code puts a handrail 34 to 38 inches above the nosing line and asks for a landing guard at least 36 inches tall, but Chicago and many suburbs adopt their own rules, so those figures are a starting point to confirm, not a final answer.
A handrail and a guard do different jobs
A handrail is the graspable member you slide your hand along while climbing or descending. Its purpose is support and balance, so the rules that govern it focus on height range, continuity along the flight and a shape a hand can close around.
A guard is the barrier along an open edge, such as the exposed side of a stair or the edge of a landing or balcony overlooking a stairwell. Its purpose is fall prevention, so its rules focus on minimum height, strength and how large the openings between balusters or panels can be.
On many residential stairs, one railing does both: the top cap of the guard is shaped and positioned to serve as the handrail. On others, especially stairs enclosed by walls on both sides, there is a wall-mounted handrail and no guard at all. Open stairs with tall landings often need both, with a guard at the landing that transitions into a handrail down the flight. Knowing which condition each part of your stair falls into is the first step in setting heights.
Where stair railing height is measured from
Heights along a stair are not measured from the treads at random points. They are measured from an imaginary sloped line that connects the leading edges, or nosings, of the treads. Picture a straight edge laid across the front edges of every step; the railing height is the vertical distance from that line up to the top of the rail.
This matters for two reasons. First, if you measure from the back of a tread instead of the nosing, you will get a number that looks taller than the real height. Second, on landings and level floors, there is no nosing line, so guard height there is measured from the walking surface itself. One continuous railing can therefore be compliant on the flight and too short at the landing, or the reverse, unless the transition is detailed with care.
What the model residential code sets for handrail height
Many US jurisdictions base their residential rules on the International Residential Code, published by the International Code Council. In the 2021 edition, Section R311.7.8.1 states that handrail height, measured vertically from the sloped plane adjoining the tread nosing, shall be not less than 34 inches and not more than 38 inches.
That section also includes exceptions that matter for custom work. A volute, turnout or starting easing is allowed over the lowest tread, and where handrail fittings or bendings create a continuous transition between flights, at winders or from handrail to guard, the height at those fittings may exceed 38 inches. Those exceptions are what make a traditional curled starting step or a smoothly ramped rail possible without breaking the rule.
Guardrail height in residential stairs and landings
The 2021 IRC defines when a guard is needed in Section R312.1.1: open-sided walking surfaces, including floors, stairs, ramps and landings, located more than 30 inches above the floor or grade below at any point within 36 inches horizontally of the open edge.
For residential guardrail height, Section R312.1.2 requires guards at open-sided walking surfaces to be not less than 36 inches high, measured above the adjacent walking surface or the line connecting the nosings. Its exceptions allow guards on the open sides of stairs to be not less than 34 inches measured from the nosing line, and where the top of the guard also serves as the handrail on the open side of a stair, it must fall between 34 and 38 inches from that line.
Under this model code, then, the landing guard is often taller than the stair guard it connects to. That height change is one of the details a railing drawing has to resolve, usually with a ramp, an easement or a taller newel at the landing.
Guards also carry limits on the size of openings between balusters and on structural load. Those requirements shape baluster spacing and how newels are anchored, and they belong in the same code check as the heights.
Why Chicago projects start by confirming the adopted code
Local practice changes the answer. The City of Chicago does not adopt the IRC wholesale for houses. It publishes its own Chicago Construction Codes, including the Chicago Building Code (Title 14B), which is based on the 2018 International Building Code with local amendments. Suburbs on the North Shore and elsewhere adopt their own code editions and amendments as well.
The result is that the figures quoted above are a useful reference for how stair handrail requirements are typically framed, but they are not automatically the numbers that apply to your project. Codes vary, and the governing handrail height code, guard height and opening limits for any stair are the ones your jurisdiction has adopted, confirmed with the building department or the project's architect before the rail is drawn.
So a custom rail should be built to the code confirmed for that specific project. When an architect has issued drawings, those drawings set the requirements. When a homeowner hires a fabricator directly, the code question needs to be answered before shop drawings begin, not after the parts are cut.
Planning a new stair, or replacing a railing that no longer suits the house? TDL Custom can look over your drawings or the stair itself and talk through newel, cap and baluster options that fit the confirmed heights. Request a complimentary railing consultation on site or by video.
Existing stairs in older homes need extra attention
Much of the stair work in Chicago happens in older housing stock: greystones, frame two-flats and prewar houses in Evanston, Wilmette and Winnetka. Original railings in these buildings often predate current rules. They can be lower than today's guards, have balusters spaced wider than modern limits or rely on newels that have loosened over decades.
Whether an existing stair must be brought up to current requirements depends on the scope of work and the local rules for alterations and repairs, which is another reason to confirm with the building department. From a fabrication standpoint, the common challenges are:
Uneven treads. Settled stairs may have nosings that do not fall on a straight line, so the rail height has to be checked at several points rather than assumed.
Mixed conditions. An original lower flight may meet a remodeled upper flight with different geometry, requiring a transition piece.
Preservation goals. Owners often want to keep a historic newel or profile. A new rail can sometimes be raised with a matching cap or a discreet secondary handrail, though the approach has to satisfy the governing code.
Turning confirmed heights into a buildable rail
Once the governing dimensions are known, the railing drawing translates them into parts. The nosing line is established from a site measure of the finished treads. Newel heights are set so the handrail meets them at the correct elevation. Landing guards are drawn at their own height, and the transitions between flight and landing are detailed with fittings or bends. Baluster lengths change along the rake, so each is cut to its own position, not to one stock length.
The millwork installation plan matters at this stage too. Newels need solid anchorage into framing, which may mean opening a floor or adding blocking before finishes are complete. On a renovation, coordinating that with the general contractor early keeps the stair from turning into the last open item on the job.
Getting the height right the first time
The cleanest custom rails come from a short routine: identify which parts of the stair need a handrail, which need a guard and which need both; measure from the nosing line on the finished stair; and confirm the code your jurisdiction has adopted before anything is drawn. The model code gives a sense of the ranges, but the local answer governs.
Working with architects, contractors and homeowners, TDL Custom fabricates and installs custom stair railings for residential projects across Chicago and the North Shore. To talk through a stair of your own, phone (773) 433-0042 or send us the plans and a few photos of the flight.
Frequently Asked Questions
Do both sides of a stair need a handrail?
Not always. Many residential codes require a handrail on at least one side of a flight once it reaches a set number of risers, and wider stairs or certain building types may require one on each side. Check the adopted code for your project, since the trigger points differ between residential and commercial rules.
Can a wall-mounted handrail be lower than the guard on the open side?
Yes, and it often is. A guard that does not serve as the handrail can be taller than the handrail range, and the handrail can be mounted separately within its own range. Some stairs use a tall guard on the open side and a wall rail on the other.
Does a short stair with only a few steps need a guard?
It depends on the height of the open edge. Guard requirements are triggered by the drop to the surface below rather than by the number of steps, so a short stair beside a low drop may not need one while a landing over a stairwell will.
Is a decorative handrail profile allowed if it is hard to grip?
Codes regulate handrail shape and size so that a hand can grasp it firmly. A wide, flat cap may look good but fail that test. A common solution is to keep a decorative cap on the guard and add a graspable handrail profile where the code requires one.
Who is responsible for confirming the code on a custom railing?
On permitted work, the architect or designer of record usually establishes the requirements, and the building department has the final say. The fabricator builds to those confirmed requirements. When there is no architect, raise the question at the start so the rail is drawn to the right numbers.